Re: Actual Activity Rate Calculation Project wise

$
0
0

Thanks Ajay for quick replay....

 

Unfortunately CO and PS BBPs are signed with client proposal, PS consultant is not ready to create project wise WC. his concern if new project starts again need to create new work center ever time so he rejected creating project wise work centers(According me also He is right).

 

I explained to client what are the disadvantages if create project wise cost center, Client has been doing in excel what they proposed so they stick on their proposal.

 

 

Ajay, is there any other solution to achieve my client proposal?

 

Thank you...